The chronology of the preparation of the mooring, first implemented by OOO “Stevedoring Yamal” in 2017:

03/12/2017 OAO YASHG provided documents for the theoretical training of Stevedoring Yamal employees on the operation of mooring mechanisms located on technological berths – the scheme included the assembly of 22 fast-acting mooring devices MAMPAEY Offshore Industries (11 from the tank and 11 from the stern of the ship)

03/21/2017 At TP № 2 representatives of JSC “YaSGG” conducted test exercises with mooring mechanisms with employees of “Stevedoring Yamal”. There are lists of employees for their verification and admission to the terminal

03/27/2017 OJSC “YaSGG” provided communication facilities for coordination of works